U.S.
shipbuilders continue in that role, though the playing field has changed.
Modern-age governmental cutbacks and formidable overseas competition have
reduced the number of U.S. yards and yard owners. While U.S. shipbuilders
are today capable of producing larger, more sophisticated ships than ever,
they no longer lead the world in output. A cyclical business dependent on
multi-million-dollar contracts, particularly with the government, the U.S.
shipbuilding industry has had to redefine itself to remain competitive.
National
Steel and Shipbuilding Co. (NASSCO), San Diego, CA, is one example of how
the U.S. shipbuilding industry is working in new ways to achieve higher
levels of quality and timeliness. A full-service shipyard offering ship
design, construction, repair and conversion, NASSCO has focused on how to
control or eliminate the costly delays that plague many shipbuilding
operations. Delays that were once considered inevitable due to the custom
nature of shipbuilding, are being ironed out of the process at NASSCO,
thanks to the company’s serious commitment to TPM.
“We
looked at all the things that were getting in the way of our objective to
produce ships on schedule on budget,” says Fred Hallett, senior vice
president and CFO. “We needed to meet not just the delivery of the ship,
but all the interim schedules so that if a piece of pipe is supposed to be
delivered from
the pipe shop to ‘on block’ at 8 o’clock on a Tuesday morning, that
piece of pipe gets delivered at 8 o’clock in the morning on Tuesday
because there’s a worker standing out there ready to put it in place.”
The
problem at NASSCO was that, for years, the pipe wasn’t there when it was
needed.
Efforts
to control the delays, such as Quality Circles and TPM, were attempted, but
with minimal success. It was not until 1997, when a dedicated TPM position
was created and
filled,
that the shipyard began to understand where it needed to make changes, how
to
make
the changes, and, most importantly, how to ensure that the positive effect
of the changes became permanent.
The
switch to full-time TPM came after the company streamlined its production
process. “We had no organization,” says Geno Martinelli, area manager of
the pipe fabrication and sheet metal shops. “Our processes were not in
control.” But when the pipe fabrication shop was reorganized into
work cells, he says, “We had an opportunity to see what our capacity was
in each category of the product we were building.” Projects were started
on time and quality improved.
“But
our bottleneck was delivery,” says Martinelli. “No matter what our
schedule was, we could never meet it because our equipment uptime was only
about 70%. Every day, something was wrong. It was a fire drill.”
Martinelli
explains that when production factors were improved, “maintenance surfaced
right to the top” as the reason why the shop still had problems. “I
started tracking maintenance availability time by equipment,” he says,
“because I was being held accountable for why we still weren’t meeting
our goals.” He describes it as a “big eye opener” when he realized
that key pieces of equipment such as the large pipe bender (the “big
bender”) were down 26% of the time.
It
was at this point that NASSCO “stepped up to the plate,” as Martinelli
says, and hired a full-time TPM expert in November 1997. Enrique Mora,
came to NASSCO with more than 30 years experience in a variety of
manufacturing fields. He also knew how to start a TPM program, gain support
for it and keep it going.
“I
had been in the sugar industry,” says Mora, “which is similar to
shipbuilding in that it uses big machines that are expensive to replace.
They need to work for many years, so you have to keep them in the best
condition possible.” Mora had also been supervisor of plant engineering at
Ford Motor Co. foundry, engine and truck-assembly plants in Mexico, where he
had been responsible for training personnel and implementing preventive
maintenance programs. According to Hallett, Mora’s hiring was a key part
of several changes undertaken at NASSCO to address the issue of
reliability.
“TPM
is a piece in a complex puzzle of everything that has to happen for us to
deliver ships on time,” he says. “And to deliver them on time 12 months
from now means that today, there are 5,000 pieces that have to go out to the
yard, at the right place at the right time with the right engineering.”
The
initial results of NASSCO’s TPM program under Mora’s guidance were
impressive. ‘The first year resulted in a 5%
reduction in base maintenance costs, says Jim Clark, general
supervisor/maintenance. “But more importantly, we gained in improved
equipment uptime. Cost of improved production can be 10 times the
maintenance cost saved.”
For
example, uptime on the big bender — Mora’s first project — went from
74% to 99%, thanks to an equipment “re-standardization” process, which
involves a complete breakdown, cleaning, repair and reassembly of the unit.
Subsequent TPM activities on other pipe benders resulted in zero downtime.
Also, the set-up time for dies on the big bender (which are changed as
different sizes of pipe are put on the machine), were reduced from 90
minutes to less than 20 minutes, thanks to TPM-SMED inspired design
modifications. These included the addition of a work table and small bridge
to allow the operator to remain on one level. Faster set-up time has allowed
the yard to meet the very important just-in-time requirement for parts.
“In
the past they built all the pipes they would need for a ship in six
months,” says Mora. “Now they build them just-in-time, which allows them
to accommodate design changes and have them ready as close as possible to
the application in the ship.”
In
the first quarter of 1998, the pantograph (a large, computer-controlled
torch that cuts precision ellipses in pipe) was down for 31 hours. After a
fourth-quarter 1998 TPM re-standardization, its downtime has been zero.
TPM re-standardizations have also been conducted on a plasma cutter in the
sheet metal shop, a 1,000-ton press, two press brakes, a 6-ft. roller and several weld positioners, all of which have
experienced little or no downtime since.
The
re-standardization process typically uncovers problems both big and small,
particularly on equipment that has never been analyzed in detail. The
pantograph, for example, had regularly produced jagged, imperfect cuts that
required additional hand grinding before welds could be made. TPM procedures
revealed that the poor-quality cuts occurred because the machine was set up
for an electrical setting that was higher than specification. A simple
reduction in amperage — the need for which went unrecognized until time
was taken to delve into machine details — put the pantograph back within
specifications and allowed it to make clean cuts that could be welded
without further work.
TPM
on the job...
Most
of the TPM work at NASSCO is conducted by members of the central maintenance
shop, a 129-man unit headed by Jim Clark. The 21-year NASSCO veteran says
the yard’s TPM program has inspired a significant shift in worker attitude
which has ultimately made his job easier. “The attitude among machine
operators prior to TPM,” says Clark. was, ‘We run the equipment, we
break the equipment and [maintenance] fixes the equipment.~ After TPM,
it’s ‘We are all responsible for the equipment performance and
productivity.’ The TPM teams work to maximize overall equipment
effectiveness. In the process, the operators become very knowledgeable about
their equipment and perform normal daily maintenance of the equipment after
the TPM event.”
To
start a TPM event, Mora
“borrows” maintenance people as he needs them to conduct a machine
re-standardization process. He’ll schedule one of the yard’s critical
machines for TPM at a time when the unit can be off-line for the required
two to four weeks needed for a complete cleaning, breakdown, repair and
reassembly. He then conducts classroom training sessions for the maintenance
crew and operators who will be working on the machine.
“This
week I’ll be training those who will be doing the weld positioners,”
says Mora. “First I’ll gather the materials I need to show them the
parts and I tell them the machine will have to be disassembled and that we
expect to find bad bearings perhaps, and that they will need to be
cleaned or replaced. We go through everything about the machine. If there is
a complex electrical system, we get the blueprints and show the electricians
and the rest of the crew how this system operates so our people become
familiar with it. Then we move to the hands-on training.”
After
steam-cleaning the machine, “We start immediately discovering
discrepancies, like loose or missing bolts or missing covers or leaks in
pipes, fittings and hydraulic motors,” says Mora. “All elements that can
have some discrepancy are discovered. We keep working at these, and at the
same time, I keep training the crew in the philosophy of TPM. The first
thing they learn is that TPM is going to make their jobs easier, faster,
safer and more productive.
Mora
says training sessions usually include the senior operator, another
member of the department who may eventually be assigned to operate that
machine. one mechanic and one electrician. “Sometimes we get more people
from production,” says Mora, “and they all undergo this
training.” During the hands-on phase, Mora works directly with them. “I
put my coveralls on, and we go watch the machine and clean it and write
down the discrepancy tags, then we concentrate on those. Sometimes we take
pictures.”
Mora
prepares a report on the completed procedure, which is posted on the
company’s intranet for view at any time. The unit is then painted blue,
thus serving as a constant - and growing - visual
reminder to workers of the positive effects of TPM.
“The
idea is to return the equipment to original condition or better,” says
Mora. In the process, custom design changes are often made, many of which
are inspired by operator suggestions. For example, the work table and small
bridge that were built and welded to the big bender were key reasons
big-bender set-up times were reduced. A planned improvement is to construct
a monorail to transport the dies and mandrels to the big bender. Currently,
those heavy parts must be picked up and moved by traveling crane.
Similarly,
a stairway was added to the 6-ft.-high pantograph to improve worker access
to the machine. Other examples include a ramp that was added to the sheet
metal shop’s iron shear machine which diverted cut metal parts to an area
easily accessible by the operator. Also in the sheet metal shop, a wheeled
work table was built for press plate operators which allows them to slide
mandrels from the table to the exact level of the machine. Prior to the
table, operators had to lift the large mandrels from storage to the machine.
Anything that cuts even a few minutes of labor time results in significant
savings at NASSCO, where the average hourly wage is $17.
The
TPM effort at NASSCO also embraces concepts that boost productivity by
improving morale. These include changes as simple as upgrading the worker
locker room with new lockers and a fresh coat of white paint.
“The
old philosophy was to paint the walls brown so dirt didn’t show,” says
Mora. “Now we paint them white.” In the carpentry shop, where all
machinery has been re-standardized through an internal TPM program (not
conducted by the maintenance department), the contrast of the blue equipment
against the background of all-white walls creates a clean, modern look not
typically associated with shipyards.
“These
are things the workers acknowledge that the company is doing for them,”
says Mora, “that TPM is doing for them. TPM is helping them do their job,
and that’s what this is about.”
Implementing
TPM
Implementing
a multiple-tiered program like TPM always faces challenges, but particularly
in a diverse work environment like a shipyard. “There was the natural
resistance you would expect from some employees,” says Clark. “But
overall, the program was well accepted and supported by both the
maintenance department and the production departments. I think the key
to our success was upper management support and the selection of a TPM
coordinator. We were lucky that Dick Vortmann [NASSCO president]
was and still is the chief flag waver for the TPM program.
Martinelli
says proof of management support is visible. “It’s not uncommon to see a
vice president or someone at that level right in the machine finding out
what we’re doing, “he says, “and that’s encouraging.”
When
Mora took over as TPM coordinator, however, he needed to convince the
maintenance staff and those who worked in departments where TPM
would take place that the new program was a good thing.
“People
are sometimes afraid that TPM will take their jobs,” he says. “On the
contrary, the idea of TPM is to create a higher level of maintenance, that
maintenance personnel are not repairmen, but the up keepers of the
equipment. They need higher levels of skill to perform in this new
environment. I told them the breakdowns are to be eliminated, not the
maintenance people.”
Mora
says that since implementing TPM at NASSCO, “The operators have a better
attitude than you could have found a few years ago. They keep their
equipment cleaner and they are proud of what they are
accomplishing.” He adds that the maintenance department assists “the
moment I need a mechanic or an electrician. If you don’t have that kind of
support, you can do nothing.”
It’s
different from pre-TPM days, says Martinelli, “when you would always see a
maintenance guy in the shop. You never see that anymore. We know when they’re
going to be there now because we’re planning our maintenance instead of
reacting.”
TPM into the future
Mora’s
plans for NASSCO’s TPM program are far reaching. For one thing, the age
of the machinery at the shipyard — an average of 20 years — and prohibitive
replacement costs demand that machinery be well cared for. “Many of
our machines have been upgraded to computer numeric control with the help of
good suppliers and our own technicians,” says Mora. “The operating
principles of new machines are not greatly different than the older ones,
and the old machines often have stronger structures, so we apply the best of
recent technologies and keep the old hardware.” Machinery like the
yard’s 45-ft. roller (used to
shape steel hull plates) was custom-built in the 1950s in Scotland, says
Mora, “and would be hard to replace, so we keep upgrading it and it
pays.”
Mora
also envisions a shipyard where even hand tools will be subjected to
operator-based TPM.
“We’re
getting to the point where each welder will take care of his machine or his
tool,” he says. “This could be three or four years from now. We’ll
have everyone who is now grinding plates in the yard come to a class where
they’ll take apart their grinder and replace the bearings and put them
back together. This is what autonomous maintenance is all about, where the
user of the machine really becomes the owner of the machine. After that,
they really take care of it.”
Hallett
says TPM has helped put NASSCO on a course to becoming a
world-class shipyard. “We have taken the first steps down a road to
improved productivity. Our next task is to walk farther down that road to
get additional, significant improvements in schedule, quality and
productivity. We believe that’s possible, that we can get a lot better.”
Hallett
adds that the yard’s motto is to be the best in the world. “We believe
American shipyards used to be the best in the world,” he says. “We’ve
visited other yards around the world and see no reason why we can’t be as
good as they are. .Are we there yet? No, but we’re committed to continuous
improvement to get there. Come back here in a year or five years and
you’ll really be impressed.”